CleanSpark posted a $987.1 million net loss for fiscal 2026, reversing a roughly $365 million profit a year earlier, as Bitcoin production and revenue fell. Annual revenue dropped 25% to $576.5 million, while fourth-quarter revenue fell 46% year over year to $120.9 million. The miner reported a nearly $9.8 million profit for the latest quarter.
Why it matters
CleanSpark mined 7,253 BTC during the fiscal year, down 8% from the prior year, as its average hashrate fell 21% to 36 EH/s. The company is shifting toward AI infrastructure, joining other Bitcoin miners seeking to develop data centers alongside their mining operations.
Its flagship Sandersville, Georgia, data center is fully funded with a 20-year, $6.6 billion lease. The first data hall is expected online by November 2027. CleanSpark is also looking to develop 885 megawatts of Texas power capacity for AI infrastructure leases.
Market impact
The company ended the quarter holding 13,530 BTC, valued at $1.1 billion at the time. That holding has since fallen to roughly $812 million as Bitcoin traded below $60,000. CleanSpark has the tenth-largest Bitcoin treasury among publicly traded companies.
CLSK shares fell 7.5% on Tuesday before the earnings release and were mostly flat after hours. The stock is down 55% year to date. CleanSpark also reported $30.6 million in proceeds tied to derivatives during the fiscal year.
Frequently asked questions
-
How did CleanSpark's annual revenue and quarterly profit compare?
Annual revenue fell 25% to $576.5 million, while fourth-quarter revenue dropped 46% year over year to $120.9 million. The company reported a nearly $9.8 million profit for the latest quarter.
-
How much Bitcoin did CleanSpark mine during fiscal 2026?
CleanSpark mined 7,253 BTC, down 8% from the prior year. Its average hashrate fell 21% to 36 EH/s.
-
What happened to the value of CleanSpark's Bitcoin treasury?
Its 13,530 BTC holding was valued at $1.1 billion at quarter-end. The value has since fallen to roughly $812 million as Bitcoin traded below $60,000.
-
What is CleanSpark developing for AI infrastructure?
Its Sandersville, Georgia, data center is fully funded with a 20-year, $6.6 billion lease. The company is also looking to develop 885 megawatts of Texas power capacity for AI leases.
-
How did CLSK shares react around the earnings release?
CLSK shares fell 7.5% on Tuesday before the release and were mostly flat after hours. The stock is down 55% year to date.
TheBlock