US Data Center Construction Starts Fall 28% in Q3

An October rebound complicates the outlook for an AI infrastructure buildout estimated at $1 trillion.

US Data Center Construction Starts Fall 28% in Q3
US Data Center Construction Starts Fall 28% in Q3

US data center construction starts fell 28% in the third quarter of 2026, with developers beginning facilities representing 8.4 gigawatts of power capacity, down from a record 11.7 GW in the prior quarter, according to Cleanview. It was the first quarterly decline in more than a year.

Starts fell to 65 buildings from 96, although the quarter was still Cleanview's third-highest on record and capacity was up 55% from a year earlier. Cleanview founder Michael Thomas estimates that data centers started this year will cost about $1 trillion to build and equip.

October starts rebounded to 4.6 GW, the second-highest monthly total recorded by Cleanview. Thomas said it was too early to call the Q3 decline a lasting slowdown. If October's pace continues through November and December, fourth-quarter starts could reach a record 14 GW.

Frequently asked questions

  1. How much data center capacity began construction in Q3?

    Developers began facilities representing 8.4 GW of power capacity in the third quarter of 2026, down from 11.7 GW in the preceding quarter.

  2. How did Q3 construction starts compare with a year earlier?

    Capacity starting construction was up 55% from the same quarter a year earlier, despite the decline from Q2.

  3. How many data center buildings began construction in Q3?

    Construction started on 65 buildings, down from 96 in the preceding quarter.

  4. What happened to data center construction starts in October?

    Developers started facilities representing 4.6 GW of capacity, the second-highest monthly total in Cleanview's records.

  5. What would it take for Q4 construction starts to reach 14 GW?

    Cleanview founder Michael Thomas said starts could reach a record 14 GW in the fourth quarter if October's pace continued through November and December.